Jetties and marinas

Jetties, pontoons and marinas on screw piles

A jetty or boathouse stands in a soft bed and has to stay straight for years. We screw piles through the water down to firm ground: no dewatering, no concrete curing in the water, and the bank stays untouched.

Calculate your foundation Request a quote

Finished timber jetty on screw piles by the water

Why no concrete?

  • No dewatering and no concrete in the water
  • Through silt and soft ground down to firm ground
  • From the bank, by hand or from a pontoon
  • Ready to load at once
  • Removable if the jetty is ever moved

See the jetty →

Which foundation?

Screw piles

Down to the bearing layer, with extensions if needed.

By hand

In a marina we also install smaller piles by hand, without a heavy machine.

Protection

In the zone where the water rises and falls we choose a thicker wall or coated piles.

How it works

How it works on site

  1. AssessmentWe look at the bank, water depth and bed.
  2. MachineFrom the bank, by hand or from a pontoon.
  3. Screwing inThe piles go through the water down to firm ground.
  4. BuildingBearers and boards can go on the piles at once.

Frequently asked questions

Is a permit needed?

Work at or in a watercourse often needs permission from the water authority. Check beforehand.

Do piles rust in the water?

In the splash zone we choose a thicker wall or coated piles.

Can it be done from the bank?

Often yes. Otherwise from a pontoon, as for the boathouse in Lier.